11.7. Activity Preemption
An ongoing activity may be preempted by a higher-priority task requiring a resource used by the ongoing activity. In such a case, the activity is either aborted or suspended, and the required resource is released from it and allocated to the higher-priority task. A suspended activity may be later resumed when a resource of the required type becomes available again.